Eisenhower Inn Water System Treatment Facility Renovation

Dawood provided engineering services to assist the Client in complying with a Consent Order Agreement (COA) from the Pennsylvania Department of Environmental Protection (DEP), which came with the property purchase from the previous owner. A new Emergency Response Plan and Operation and Maintenance Plan which comply with the Department’s requirements were prepared, submitted, and approved. This brought the water system into compliance with the COA. A review of the existing water system facilities was also performed, and a report with recommendations for system improvements was provided to the Client for their consideration.

Location

Gettysburg, PA

Status

Completed in 2017

Solutions

Regulatory Negotiation Assistance, Corrective Action Planning, Consent Order Agreement Progress Reports, NPDES Permit Transfer and Amendment, WQM Part II Permit Application